Medium and Low-pressure Natural Gas Pipeline System

Ongoing maintenance, including periodic measurements

Pipelines Details: Dia. from 2″ to 18″, in various lengths.

Client: Merimon Natural Gas North Ltd

High Pressure Natural Gas Pipeline Ramat Hovav – Ashalim Section

Complete engineering design for Corrosion Protection and Cathodic Protection

Pipeline Details: Dia. 36″, Length 33.1 km

Client: Israel Natural Gas Lines Ltd

Year: 2026

New offshore Off-Load 16” and 24” distillates and fuel oil and two 10” LPG pipelines. Includes Multi-Buoy Mooring (MBM) and Pipeline End Manifold (PLEM) to onshore Costal Valves Stations (CVS)

Preparing the engineering Corrosion Protection Basis of Design (BOD)

Client: Israel Ports – Development and Assets Company Ltd (IPC)

Year: 2024

HP natural gas 36″ Duplication K.Baroch-Dovrat

CP Design plus Design restrain systems to reduce the effects of short cut from nearby HV pilons 161 KV

Pipeline Length: 18.3 Km

Final Client: INGL

Year: 2018

Leviathan Production Platform

CP Design for three firewater pump caissons

Engineering Contractor: Wood Group – Mustang
Client: Noble Energy Inc.

Year: 2018

Charles Meyer Desalination Project

CP Design & Analysis Data for Intake Pump Stations

Engineering Contractor: IDE
Clint: Santa Barbara Municipally

Yaer: 2018

Groundings installations for 36″ eastern pipeline

CP project Management

Pipeline Length: 92 Km

Client: INGL

Year: 2018

Mount Holland Lithium Mine

MVC Desalination Unit Corrosion Assessment and Material Review

Engineering Contractor: IDE
Mount Holland Lithium Mine, Kwinana, Western Australia

Year: 2019

Formosa Project, Taiwan Seawater Reverse Osmosis Desalination Plant

CP Design for internal super duplex piping

Engineering Contractor: IDE
Client: Formosa Petrochemical Corporation (FPCC)

Year: 2019

Jenin Natural Gas Pipeline & Valve Station

CP Design

Pipeline Length: 0.78 Km

Client: Palestine Power Generation Co.

Year: 2019

HP natural gas 18″ Beer Tuvia

CP Supervision

Pipeline Length: 9.5 Km

Year: 2019

Client: INGL

Karish – Tanin onshore HP natural gas 32″

CP Design

Pipeline Length: 1.2 Km

Engineering Contractor: TechnipFMC plus TMNG

Year: 2020

Client: Energean Oil&Gas

BAZAN- Elroy 12″ Fuel Pipeline

CP Design

Pipeline Length: 11.5 Km

Client: Petroleum & Energy Infrastructures Ltd (PEI)

Year: 2020

Eshel Hanasi-Mishor Rotem 12″ and 10″ Fuel Pipelines

CP Design

Pipelines Length: 84.5 Km + 84.5 km

Client: Petroleum & Energy Infrastructures Ltd (PEI)

Year: 2020

HP 24″ natural gas pipeline to Gaza Palestine

CP Design

Pipeline lenght: 40 Km

Client: INGL

Year: 2020

Anode-bed installation and CP arrangements for pipeline under highway

Project Management and Tecnical Supervision of anode-bed installation and CP arrangements for pipeline under highway

Client: INGL

Yaer: 2020

HP 24″ natural gas pipeline to Jerusalem

CP Supervision

Pipeline Lengh: 17 Km

Client: INGL

Year: 2018

Leviathan Onshore Development

CP Coordination activities, Supervision, Commissioning and Acceptance Tests

Pipeline Length: 25 Km

Client: Noble Energy Inc.

Year: 2019